CIVIL WORKS
MONTHLY PROGRESS REPORTS
CW1 – Status of Completed Civil Works
Reporting month:NOVEMBER 2008
| Sl. No. (1) | Name of works (2) | Method of Procurement NS/NCB etc. (3) | Value of Contract (4) (Rs. in million) | Date of Completion Scheduled (5) | Date of Completion Actual (6) | Actual Cost of Work ## (As Completed) (7) (Rs. in million) | Remark If Any (8) |
| 1 | Extension Block of Metallurgical Engineering Department | NS | 2.198 | October 2006 | November 2006 | 2.246 | NIL |
| 2 | Refurbishing Electrical Gallery Hall | NS | 2.114 | December 2006 | November 2006 | 2.105 | NIL |
| 3 | Refurbishing A13 Lecture Hall | NS | 1.622 | December 2006 | November 2006 | 1.442 | NIL |
| 4 | Refurbishing of computer lab and Instruments laboratory in Chemistry dept | NS | 0.168 | October 2006 | October 2006 | 0.173 | NIL |
| 5 | Replacement of A/C sheets with profiled colour coated galvanized sheet in Workshops | NS | 1.916 | December 2006 | November 2006 | 1.895 | NIL |
| 6 | Renovation of Toilets in various Departmental buildings. | NS | 1.722 | December 2006 | November 2006 | 1.970 | NIL |
| 7 | Renovation works in Electrical Machines laboratory (provision of MDB Switches) | NS | 0.319 | February 2006 | October 2006 | 0.350 | NIL |
| 8 | Extension of Civil Engineering Class Rooms | NS | 2.228 | January 2006 | October 2006 | 1.884 | NIL |
| 9 | Renovation of Seminar Hall – Production Engg. | NS | 0.384 | February 2006 | December 2006 | 0.368 | NIL |
| 10 | Renovation of Chemical Engg. lab | NS | 0.285 | February 2006 | December 2006 | 0.223 | NIL |
| 11 | Refurbishing of Lecture Hall in EEE dept. | NS | 0.168 | March 2006 | December 2006 | 0.157 | NIL |
| Grand Total | 13.115 | 12.813 |